Project Magenta Next Generation Simulator
Last Updated: November 15, 2005

Simulator Project Management    

General

  • Research & Development
  • Defining key suppliers
  • Budgeting / Schedule
  • Construction
  • Testing

 

Timeline

July 2004 Research / Design / Development
August 2004 Defining key suppliers / Budgeting / Schedule
October 2004 Simulator Base Construction
November 2004 Cockpit Internal mouldings finishing
December 2004 Collimated Display System Arrival
January 2005 Overhead Panel Construction
January 2005 Computer Network Installation
February 2005 Collimated Display System tests
February 2005 Primary Flight Control Specification finalised and Order
February 2005 Auto Throttle System Finalised and Order
March 2005 Main Panel installation of Instruments / Gear / Annociators
March 2005 Overhead panel completed / I/O tests completed & software intergration
March 2005 Primary Flight Controls Delivery
March 2005 Flight Controls Installation
March 2005 737 Shell Order
April 2005 Throttle Unit Arrival
April 2005 MCP & EFIS Installation in Main Glare Shield
April 2005 Ground Steering System
April 2005 Auxilary systems installation: Air / Electric / Lighting
July 2005 Throttle Unit Installation / Software development and testing
October 2005 Shell, Structure and mouldings fitting
November 2005 Collimated Displays lifted and fixed into position
November 2005 Finishing and Testing